Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Pilot project alleviates housing backlog in Gobabis

Home National Pilot project alleviates housing backlog in Gobabis
Pilot project alleviates housing backlog in Gobabis

Edgar Brandt

More than 1100 households in the town of Gobabis have received land through an existing institutional partnership between the Shack Dwellers Federation of Namibia (SDFN) and the Namibia Housing Action Group (NHAG) that resulted in a settlement upgrading in the eastern town. Other key partners include the Gobabis municipality and the Ministry of Urban and Rural Development. With support from the German Cooperation Agency (GIZ) and other international partners, the project became part of government’s Flexible Land Tenure (FLT) pilot project.

Thus far, 20 houses have been completed and a further 10 brick-and-mortar structures are currently under construction. Earlier this month, 988 residents were presented with certificates of their land hold titles through the FLT project.

The Namibia University of Science and Technology’s departments of Architecture and Spatial Planning; and Land and Property Sciences, also played key roles in bringing the project to fruition. NUST students and lecturers participated in different aspects of the project as a case study, which resulted in journal publications as well as Masters and PhD dissertations for the NUST students. 

According to Guillermo Delgado, the Land, Livelihoods and Housing Programme Coordinator at NUST’s Integrated Land Management Institution (ILMI), the process started around 2012 when data was collected by residents of the area and based on their findings, discussions followed amongst various stakeholders to develop the settlement called Freedom Square. 

Also in 2012, a Memorandum of Understanding between the Gobabis municipality, SDFN and NHAG, was signed which laid the groundwork for a series of “planning studios” with town and regional planning students in NUST’s Department of Architecture and Spatial Planning.

In these studios, NUST students analysed the site, mapped infrastructure and features and engaged community members to design layouts of “re-blocking” the settlement structures into a formal setting.

The urban and rural development ministry then availed N$10 million to install infrastructure (water and sewer) at the site through community training. Communities excavated the trenches and even installed their own water lines and constructed manholes through training. Additional funding was sourced from a Latin American, African and Asian Social Housing Service in Europe, called Selavip, to purchase 200 prepaid water
meters.

“A contractor, KSP assisted with excavation of sewer trenches and offered to lay sewer pipes at no cost. After the completion of the services, pressure tests on water and sewerage lines were done and passed, and services were handed over to the municipality. Before installing the services, the community requested that they be provided with prepaid water meters instead of conventional water meters,” said Delgado. -ebrandt@nepc.com.na

w