Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Windhoek-Hosea Kutako road on track – Lutombi

Home National Windhoek-Hosea Kutako road on track – Lutombi

Kuzeeko Tjitemisa

Windhoek-Roads Authority (RA) Chief Executive Officer, Conrad Lutombi has announced it has made significant progress in the first phase of the Windhoek-Hosea Kutako road upgrade to a dual carriageway.
Addressing the media last Friday, he said project is being constructed in two phases comprising of phase one, which consist of the upgrade to a dual carriageway over urban portion between main road 49 (Mandume Ndemufayo Avenue) and the extension of Sam Nujoma drive to the south east of Windhoek.

He said under phase one, 8.4 kilometers will be constructed to full a dual carriageway standard and in addition, ten new bridges and three interchanges will also be constructed.

He also said, two existing bridges over the railway line and the Arebbusch River will be widened and rehabilitated to increase its lifespan. “I am happy to share with you that work is progressing well,” he said.
He said phase two will start from the interchange of Sam Nujoma Drive to Hosea Kutako International Airport, covering a distance of 34 kilometers.

Lutombi says recently they received complaints from inhabitants living in and around the Auasblick, Cimbabasia, Olympia and Kleine Kluppe residential areas.

He said these complains are mainly about the excessive vibration caused by compacting equipment, possible damage to residential property as well as noise and dust pollution.

He said in light of such challenges, adequate public consultations were done before the commencement of the project and continuous public meetings are being held with all relevant stakeholders.

He said during these sessions, stakeholders were also informed of the fact that the proclamation of this road was done in the 1970’s and the construction of this project has been on the City of Windhoek’s plans.

Lutombi says the authority have taken note of the issues raised and the contractors have implemented measures which include drilling and blasting can contractually be carried out, under very strict blast energy control.
He said the contractor has, however, adopted pneumatic hammer breaking down to reduce vibration effect at his own costs.

“It is important to mention here vibration is required to compact material, without which the freeway cannot be constructed,” said Lutombi.

“Even though we are experiencing a few inconveniences. This is unfortunately the nature of this type of construction,” he said.

He said the benefits of this project for Namibia and SADC as a whole, far outweighs the inconveniences which are temporary.

“Let me use this platform to apologise for the inconveniences caused to those living alongside this project and also appeal to all the contractors to ensure a timely completion of this project,” he the RA chief.
He said the envisage completion date of this project is October 2019.