Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Section of Luhonono road to be completed by December

Home National Section of Luhonono road to be completed by December

KATIMA MULILO – Section A of the multimillion Namalubi-Isize-Luhonono road is expected to be completed by December after the contractor made massive progress after floodwaters subsided.

Zambezi Regional Governor Lawrence Sampofu revealed in June that due to the complexity of the multimillion road, the project has been divided into two sections. Section A, which is about 24 km long, covers the road from Namalubi to Isize including the access road to Kalimbeza rice project. 

During the road inspection last week New Era observed that the access road which is about 2.5 km has already been completed while massive progress has been made on the main road.

The Deputy Minister of Works and Transport James Sankwasa was satisfied with the progress made so far. He noted that although people feel the road has been delayed, it is justifiable due to the complex nature of the project, as various adjustments were done after previous floods overtopped the road on various sections.

“We want to do proper quality work. When the road is finished we don’t want to come back after a year and redo it again. So the delay is an advantage for government and the people – it is not negative. It is intended to do a proper job. Than to rush and do a poor job,” said Sankwasa.

Section B which cover the road from Isize to Luhonono will be worked on early next year following the completion of Section A. The drainage designs of that section have been revised to include more culverts and three big bridges across deeper and bigger channels.