Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Liselo-Kongola road almost complete

Home Special Focus Liselo-Kongola road almost complete

WINDHOEK – The construction of the N$8 million tarred road stretching some 200 kilometres linking Liselo to Linyanti, Kongola and Singalamwe is almost complete.

The road from Liselo to Singalamwe is being constructed through a joint venture of Metallurgical Corporation of China (MCC) and the Roads Contractor Company (RCC).

It will be completed by end of November 2014.

According to Mumba Zitumbikwa the project manager, the construction currently stands at over 80 percent and he assured the public that the road would be ready by the start of the festive season.

The reconstruction of the tarred road that started in 2012 was expected to be completed by end of this month but was deferred to November, after the initial tar layer was removed due to its substandard condition. The road was initially designed to carry low-volume traffic.

However the delay was attributed to the lack of transportation of the surfacing stones from Zambia.

“We were challenged with the haulage of surfacing stones but now the matter has been resolved after the regional governor was engaged in talks with his Zambian counterpart. Rainfall at the beginning of the year was also another obstacle that disturbed the progress and the demining of some of the road sections that were believed still to have unexploded ordinances and ammunition,” said Zitumbikwa